The RACI matrix: responsible, accountable, consulted and informed
The simple table that settles who does the work, who answers for it, who is asked first and who is told afterwards.
What do the four letters of RACI mean?
- Responsible (R): the person or team who does the work. There can be several.
- Accountable (A): the one person who answers for the result, has the authority to approve it, and delegates the work to the R. The buck stops here.
- Consulted (C): people whose expertise or agreement is sought before the work is finished. Communication goes both ways.
- Informed (I): people kept up to date on progress or the outcome. Communication goes one way.
In PMI's terms a RACI chart is one kind of responsibility assignment matrix (RAM): a grid that links the work of a project to the people who carry it out.
What does a RACI matrix look like?
A made-up example, for illustration only: part of the go-live of a new order entry module.
| Task | CMIO | Project manager | Analysts | Nurse managers | Help desk |
|---|---|---|---|---|---|
| Prepare and approve the order sets | A | I | R | C | I |
| Build and test the module | C | A | R | C | I |
| Train the nursing staff | I | A | C | R | I |
| Go-live support | C | A | R | C | R |
A row shows who does what on one task; a column shows one role's whole load. A column full of R's may be a person who is overloaded; a column of only I's may be a stakeholder who is not engaged enough.
What are the rules of a good RACI?
- Exactly one A per task. Two A's means no one is really accountable; no A means no one is.
- At least one R per task. Otherwise the work is assigned to nobody.
- The A and the R can be the same person on a small task, in which case the cell is often written A/R.
- Keep the C's few. Every C is a person to wait for; too many slow the task down.
- Assign roles, not only names, and agree the chart with the people in it, so it holds when people change.
- Review it when the scope or the team changes.
What are RASCI and DACI?
- RASCI adds S for Supportive: people who help the R with resources or work but do not own the task.
- RACI-VS adds Verifier (checks the result against the criteria) and Signatory (signs it off).
- DACI is used for decisions rather than tasks: Driver (runs the decision process), Approver (makes the call), Contributors (give input), Informed.
The idea is the same in all of them: one owner, clear doers, and a deliberate choice of who is asked and who is told.
How does RACI relate to stakeholder analysis?
A RACI chart assigns roles on tasks to people already on the project. Stakeholder analysis comes first: it lists everyone affected by or able to affect the project and decides how to engage each. A common tool is the power-interest grid: high power and high interest, manage closely; high power and low interest, keep satisfied; low power and high interest, keep informed; low power and low interest, monitor. The project sponsor is usually accountable for the project as a whole and its business case; the project manager is usually accountable for delivering the plan.
What do candidates get wrong?
- Several A's on one task "to share approval". Accountability cannot be shared; there is one A.
- Confusing R and A. The R does the work; the A answers for it and approves it.
- Confusing C and I. Consulted is two-way and before; informed is one-way and after.
- Making the project manager A for everything. Clinical content decisions, for example, usually belong to clinical leaders.
- Consulting everyone on everything. It slows every decision and blurs ownership.
Summary for revision
- R does the work; A answers for it and signs off; C is asked before; I is told after.
- One A per task, at least one R; A and R may be one person.
- C is two-way communication, I is one-way.
- RASCI adds Supportive; DACI is for decisions.
- Stakeholder analysis (power-interest grid) decides how to engage each stakeholder.
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide): responsibility assignment matrix and RACI chart.
- A. Mendelow, Environmental Scanning: The Impact of the Stakeholder Concept, Proceedings of the Second International Conference on Information Systems (1981): the stakeholder mapping on which the power-interest grid is based.
Related free practice questions
The site files this concept under the domain Management and Leadership.
Try exam-style questions
A 20-question trial exam with an explanation for every option and a score per domain, drawn from 40 free questions. No payment method needed.
Start the trial examQuestions about the exam: CPHIMS guide · What is CPHIMS? · Exam cost · Eligibility · Passing score · Renewal · Exam day · How long to study · Is it worth it? · What is CAHIMS?
Concepts explained: HL7 v2 vs FHIR · Capitation vs fee-for-service · Safe Harbor vs Expert Determination · Incident vs problem vs change · Backup types, RTO and RPO · Privacy Rule vs Security Rule · CDS five rights · Lewin vs Kotter · SDLC and go-live strategies · Testing types · Earned value (SPI, CPI) · Structure, process, outcome · HIE models · Six Sigma vs Lean · Levels of interoperability · Bandwidth vs latency · EMTALA · Risk responses · Build vs buy · Sunk vs opportunity cost · Data governance
The four domains: Healthcare and Technology Environments · Clinical Informatics · Healthcare Information and Systems Management · Management and Leadership
Written by Adel Moustafa, About us
Written and checked against the sources above on 22 October 2026. An independent site, not affiliated with or endorsed by HIMSS. CPHIMS® is a registered trademark of HIMSS.