Earned value management: PV, EV, AC, SPI and CPI
How a project manager tells, from three numbers, whether a project is behind schedule or over budget, and what it will probably cost at the end.
What are PV, EV and AC?
- Planned value (PV): the budget of the work that was planned to be finished by the status date, from the project's baseline.
- Earned value (EV): the budget of the work that has actually been finished by that date. If 40% of a 500,000-dollar project is done, EV is 200,000, whatever it cost.
- Actual cost (AC): what the finished work really cost.
- Budget at completion (BAC): the total budget of the whole project.
The key is EV: it measures progress in money, so time and cost can be compared on the same scale. Comparing actual spending with planned spending alone says nothing about how much work was done.
What are the earned value formulas?
| Measure | Formula | What it means |
|---|---|---|
| Schedule variance (SV) | EV − PV | Negative: behind schedule. Positive: ahead. |
| Cost variance (CV) | EV − AC | Negative: over budget. Positive: under budget. |
| Schedule performance index (SPI) | EV ÷ PV | Below 1: behind schedule. 0.8 means 80% of the work planned for this date is done. |
| Cost performance index (CPI) | EV ÷ AC | Below 1: over budget. 0.8 means 80 cents of work for every dollar spent. |
| Estimate at completion (EAC) | BAC ÷ CPI | Expected total cost if cost performance continues as it is. |
| Variance at completion (VAC) | BAC − EAC | Negative: expected to finish over budget. |
Two habits make the formulas easy: EV comes first in the four basic ones (SV, CV, SPI, CPI), and a difference is a variance while a ratio is an index.
How does it work on an example?
Made-up figures, for illustration only: a patient portal project with a budget (BAC) of 500,000 dollars. At the end of month four:
- PV = 250,000 (half the work should be done by now).
- EV = 200,000 (40% of the work is actually done).
- AC = 240,000 (what that work cost).
Then SV = 200,000 − 250,000 = −50,000 and SPI = 200,000 ÷ 250,000 = 0.8: behind schedule. CV = 200,000 − 240,000 = −40,000 and CPI = 200,000 ÷ 240,000 ≈ 0.83: over budget. If nothing changes, EAC = BAC ÷ CPI = 500,000 ÷ 0.8333… = 600,000, that is 100,000 more than budgeted (VAC = −100,000; ETC = 600,000 − 240,000 = 360,000).
How is the final cost forecast?
The simplest forecast, EAC = BAC ÷ CPI, assumes the project keeps spending the way it has so far. Other forecasts assume the rest of the work will go to plan (EAC = AC + BAC − EV), or that both cost and schedule performance will weigh on it (EAC = AC + (BAC − EV) ÷ (CPI × SPI)). The estimate to complete (ETC = EAC − AC) is what is still to be spent. Which forecast fits is a judgement: a one-off problem that has been fixed points to the second, a steady pattern to the first.
How are the results read?
- Indexes: 1 means on plan; below 1 is unfavourable, above 1 favourable.
- Variances: negative is unfavourable, positive favourable.
- Schedule and cost are separate: a project can be ahead of schedule and over budget at once, for example when overtime buys speed.
- A trend matters more than one reading: a CPI that falls month after month calls for action even if it is still near 1.
Earned value works only with a sound baseline: scope, schedule and budget agreed at the start, and changed only through change control. Without it, PV means nothing.
What do candidates get wrong?
- Dividing the wrong way round. SPI = EV ÷ PV and CPI = EV ÷ AC, never PV ÷ EV.
- Using AC in the schedule index. Schedule compares EV with PV; cost compares EV with AC.
- Reading an index above 1 as bad. Above 1 is better than planned.
- Judging progress by spending. Having spent half the budget does not mean half the work is done; EV measures the work.
- Assuming behind schedule means over budget. The two are measured separately.
Summary for revision
- PV: planned work by now; EV: work actually done; AC: what it cost; BAC: total budget.
- SV = EV − PV, SPI = EV ÷ PV: schedule.
- CV = EV − AC, CPI = EV ÷ AC: cost.
- Below 1 or negative is unfavourable; above 1 or positive favourable.
- EAC = BAC ÷ CPI if spending continues as it is; ETC = EAC − AC.
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide): cost and schedule performance measurement.
- Project Management Institute, The Standard for Earned Value Management (2019).
Related free practice questions
The site files this concept under the domain Management and Leadership.
Try exam-style questions
A 20-question trial exam with an explanation for every option and a score per domain, drawn from 40 free questions. No payment method needed.
Start the trial examQuestions about the exam: CPHIMS guide · What is CPHIMS? · Exam cost · Eligibility · Passing score · Renewal · Exam day · How long to study · Is it worth it? · What is CAHIMS?
Concepts explained: HL7 v2 vs FHIR · Capitation vs fee-for-service · Safe Harbor vs Expert Determination · Incident vs problem vs change · Backup types, RTO and RPO · Privacy Rule vs Security Rule · CDS five rights · Lewin vs Kotter · SDLC and go-live strategies · Testing types · Structure, process, outcome · HIE models · Six Sigma vs Lean · Levels of interoperability · Bandwidth vs latency · EMTALA · Risk responses · RACI matrix · Build vs buy · Sunk vs opportunity cost · Data governance
The four domains: Healthcare and Technology Environments · Clinical Informatics · Healthcare Information and Systems Management · Management and Leadership
Written by Adel Moustafa, About us
Written and checked against the sources above on 22 October 2026. An independent site, not affiliated with or endorsed by HIMSS. CPHIMS® is a registered trademark of HIMSS.